  "meta": {
    "projekt": "PIL_Prov_Terminprogramm_191015",
    "quelle": "042_PIL_Prov_Terminprogramm_KiTa_Garage_250813_Strangweise_260427.xml",
    "stand": "2026-04-30",
    "datumsfenster": {
      "von": "2026-04-27",
      "bis": "2026-05-10"
    },
    "outline_levels": [
      3,
      4,
      5
    ],
    "include_milestones": false
  },
  "vorgaenge": [
    {
      "nr": 796,
      "bereich": "Ausbau Wohnungen",
      "name": "Schleifen des Parketts inkl 1 Behandlung und Abdecken",
      "start": "2026-03-23",
      "ende": "2026-05-08",
      "dauer_tage": 32.0,
      "ressource": "281.7",
      "outline_level": 3,
      "outline_number": "4.4.22",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "4961"
      ]
    },
    {
      "nr": 891,
      "bereich": "Ausbau Wohnungen 3. - 5. OG",
      "name": "Malerarbeiten",
      "start": "2026-04-08",
      "ende": "2026-05-13",
      "dauer_tage": 25.0,
      "ressource": "285.1",
      "outline_level": 3,
      "outline_number": "5.4.24",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5074"
      ]
    },
    {
      "nr": 992,
      "bereich": "Ausbau Wohnungen 3. - 5. OG",
      "name": "Schleifen des Parketts inkl 1 Behandlung und Abdecken",
      "start": "2026-04-08",
      "ende": "2026-05-06",
      "dauer_tage": 20.0,
      "ressource": "281.7",
      "outline_level": 3,
      "outline_number": "6.4.20",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5158"
      ]
    },
    {
      "nr": 993,
      "bereich": "Ausbau Wohnungen 3. - 5. OG",
      "name": "Montage Küchen",
      "start": "2026-04-08",
      "ende": "2026-04-28",
      "dauer_tage": 15.0,
      "ressource": "258.0",
      "outline_level": 3,
      "outline_number": "6.4.21",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5073"
      ]
    },
    {
      "nr": 607,
      "bereich": "Innenhof",
      "name": "Umgebungsarbeiten",
      "start": "2026-04-08",
      "ende": "2026-04-28",
      "dauer_tage": 15.0,
      "ressource": "421.0",
      "outline_level": 3,
      "outline_number": "3.3.6",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5275"
      ]
    },
    {
      "nr": 994,
      "bereich": "Ausbau Wohnungen 3. - 5. OG",
      "name": "Montage Schreinerarbeiten (Vorhangbretter)",
      "start": "2026-04-15",
      "ende": "2026-04-28",
      "dauer_tage": 10.0,
      "ressource": "273.3",
      "outline_level": 3,
      "outline_number": "6.4.22",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5159"
      ]
    },
    {
      "nr": 526,
      "bereich": "Gasse",
      "name": "Eternitmontage Laubengänge",
      "start": "2026-04-15",
      "ende": "2026-05-06",
      "dauer_tage": 15.0,
      "ressource": "224.5",
      "outline_level": 3,
      "outline_number": "2.16.6",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5352"
      ]
    },
    {
      "nr": 940,
      "bereich": "Kinderheim EG - 2. OG",
      "name": "Malerarbeiten",
      "start": "2026-04-15",
      "ende": "2026-05-06",
      "dauer_tage": 15.0,
      "ressource": "285.1",
      "outline_level": 3,
      "outline_number": "5.5.29",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5208"
      ]
    },
    {
      "nr": 1039,
      "bereich": "Kinderheim EG - 2. OG",
      "name": "Montage Holzrahmentüren",
      "start": "2026-04-15",
      "ende": "2026-05-06",
      "dauer_tage": 15.0,
      "ressource": "273.02",
      "outline_level": 3,
      "outline_number": "6.6.23",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5183"
      ]
    },
    {
      "nr": 532,
      "bereich": "Nord",
      "name": "PU-Abdichtung Nord",
      "start": "2026-04-15",
      "ende": "2026-05-06",
      "dauer_tage": 15.0,
      "ressource": "224.5",
      "outline_level": 3,
      "outline_number": "2.17.5",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "4480",
        "5352"
      ]
    },
    {
      "nr": 936,
      "bereich": "Kinderheim EG - 2. OG",
      "name": "Montage Holzrahmentüren",
      "start": "2026-04-17",
      "ende": "2026-05-11",
      "dauer_tage": 15.0,
      "ressource": "273.02",
      "outline_level": 3,
      "outline_number": "5.5.25",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5005"
      ]
    },
    {
      "nr": 951,
      "bereich": "Kinderheim EG - 2. OG / Einbau Schreinerelemente",
      "name": "Eingangshalle",
      "start": "2026-04-17",
      "ende": "2026-04-30",
      "dauer_tage": 10.0,
      "ressource": "273.3",
      "outline_level": 4,
      "outline_number": "5.5.31.9",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5248"
      ]
    },
    {
      "nr": 614,
      "bereich": "Gasse",
      "name": "Umgebungsarbeiten",
      "start": "2026-04-21",
      "ende": "2026-05-12",
      "dauer_tage": 15.0,
      "ressource": "421.0",
      "outline_level": 3,
      "outline_number": "3.4.4",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5282"
      ]
    },
    {
      "nr": 798,
      "bereich": "Ausbau Wohnungen",
      "name": "Ausbessern Türanschlüsse",
      "start": "2026-04-22",
      "ende": "2026-04-29",
      "dauer_tage": 5.0,
      "ressource": "271.0",
      "outline_level": 3,
      "outline_number": "4.4.24",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "4978"
      ]
    },
    {
      "nr": 1052,
      "bereich": "Finisharbeiten Kinderheim (Etappe 2+3)",
      "name": "Endmontage Sanitär / Elektro",
      "start": "2026-04-22",
      "ende": "2026-05-06",
      "dauer_tage": 10.0,
      "ressource": "250.0 | 232.0 | 244.0 | 243.0",
      "outline_level": 3,
      "outline_number": "6.7.1",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5182"
      ]
    },
    {
      "nr": 1000,
      "bereich": "Finisharbeiten Wohnungen Etappe 3",
      "name": "Endmontage Sanitär / Elektro",
      "start": "2026-04-22",
      "ende": "2026-05-06",
      "dauer_tage": 10.0,
      "ressource": "250.0 | 232.0 | 244.0 | 243.0",
      "outline_level": 3,
      "outline_number": "6.5.1",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5182"
      ]
    },
    {
      "nr": 1040,
      "bereich": "Kinderheim EG - 2. OG",
      "name": "Montage Brandabschnittstüren",
      "start": "2026-04-22",
      "ende": "2026-04-28",
      "dauer_tage": 5.0,
      "ressource": "273.03",
      "outline_level": 3,
      "outline_number": "6.6.24",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5182"
      ]
    },
    {
      "nr": 1049,
      "bereich": "Kinderheim EG - 2. OG / Einbau Schreinerelemente",
      "name": "Einbau Wandverkleidung inkl. Türen",
      "start": "2026-04-22",
      "ende": "2026-05-06",
      "dauer_tage": 10.0,
      "ressource": "273.3",
      "outline_level": 4,
      "outline_number": "6.6.29.4",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5331"
      ]
    },
    {
      "nr": 1050,
      "bereich": "Kinderheim EG - 2. OG / Einbau Schreinerelemente",
      "name": "Einbau Wandschränke",
      "start": "2026-04-22",
      "ende": "2026-05-06",
      "dauer_tage": 10.0,
      "ressource": "273.3",
      "outline_level": 4,
      "outline_number": "6.6.29.5",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5249"
      ]
    },
    {
      "nr": 801,
      "bereich": "Ausbau Wohnungen",
      "name": "Malerarbeiten",
      "start": "2026-04-24",
      "ende": "2026-05-12",
      "dauer_tage": 12.0,
      "ressource": "285.1",
      "outline_level": 3,
      "outline_number": "4.4.27",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5254"
      ]
    },
    {
      "nr": 820,
      "bereich": "KiTa EG",
      "name": "Montage Holzrahmentüren",
      "start": "2026-04-27",
      "ende": "2026-04-29",
      "dauer_tage": 2.0,
      "ressource": "273.02",
      "outline_level": 3,
      "outline_number": "4.5.17",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "4978"
      ]
    },
    {
      "nr": 996,
      "bereich": "Ausbau Wohnungen 3. - 5. OG",
      "name": "Malerarbeiten",
      "start": "2026-04-29",
      "ende": "2026-05-29",
      "dauer_tage": 19.0,
      "ressource": "285.1",
      "outline_level": 3,
      "outline_number": "6.4.24",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5159"
      ]
    },
    {
      "nr": 831,
      "bereich": "Finisharbeiten",
      "name": "Grobreinigung",
      "start": "2026-04-29",
      "ende": "2026-05-07",
      "dauer_tage": 5.0,
      "ressource": "287.0",
      "outline_level": 3,
      "outline_number": "4.6.2",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5006",
        "5005"
      ]
    },
    {
      "nr": 608,
      "bereich": "Innenhof",
      "name": "Belagseinbau",
      "start": "2026-04-29",
      "ende": "2026-05-06",
      "dauer_tage": 5.0,
      "ressource": "421.0",
      "outline_level": 3,
      "outline_number": "3.3.7",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5276"
      ]
    },
    {
      "nr": 609,
      "bereich": "Innenhof",
      "name": "Bepflanzung",
      "start": "2026-04-29",
      "ende": "2026-05-21",
      "dauer_tage": 14.0,
      "ressource": "421.0",
      "outline_level": 3,
      "outline_number": "3.3.8",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5276"
      ]
    },
    {
      "nr": 821,
      "bereich": "KiTa EG",
      "name": "Einbau Kunststein (Korridor)",
      "start": "2026-04-29",
      "ende": "2026-05-07",
      "dauer_tage": 5.0,
      "ressource": "281.5",
      "outline_level": 3,
      "outline_number": "4.5.18",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5005"
      ]
    },
    {
      "nr": 822,
      "bereich": "KiTa EG",
      "name": "Einbau Linoleum inkl Sockel",
      "start": "2026-04-29",
      "ende": "2026-05-07",
      "dauer_tage": 5.0,
      "ressource": "281.7",
      "outline_level": 3,
      "outline_number": "4.5.19",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5005"
      ]
    },
    {
      "nr": 1041,
      "bereich": "Kinderheim EG - 2. OG",
      "name": "Einbau Küche / 4 Stk.. Plus Regenerationsküche",
      "start": "2026-04-29",
      "ende": "2026-05-13",
      "dauer_tage": 10.0,
      "ressource": "258.0",
      "outline_level": 3,
      "outline_number": "6.6.25",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5159"
      ]
    },
    {
      "nr": 839,
      "bereich": "Finisharbeiten",
      "name": "Mängelbehebung",
      "start": "2026-05-06",
      "ende": "2026-06-04",
      "dauer_tage": 19.0,
      "ressource": "Alle",
      "outline_level": 3,
      "outline_number": "4.6.10",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "4952"
      ]
    },
    {
      "nr": 897,
      "bereich": "Ausbau Wohnungen 3. - 5. OG / Finisharbeiten",
      "name": "Grobreinigung",
      "start": "2026-05-07",
      "ende": "2026-05-18",
      "dauer_tage": 5.0,
      "ressource": "287.0",
      "outline_level": 4,
      "outline_number": "5.4.27.3",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5501",
        "4949"
      ]
    },
    {
      "nr": 834,
      "bereich": "Finisharbeiten",
      "name": "Signaletik",
      "start": "2026-05-07",
      "ende": "2026-05-18",
      "dauer_tage": 5.0,
      "ressource": "278.0",
      "outline_level": 3,
      "outline_number": "4.6.5",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "4949"
      ]
    },
    {
      "nr": 825,
      "bereich": "KiTa EG / Einbau Schreinerelemente",
      "name": "Montage Galerie",
      "start": "2026-05-07",
      "ende": "2026-05-11",
      "dauer_tage": 2.0,
      "ressource": "273.3",
      "outline_level": 4,
      "outline_number": "4.5.21.1",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "4966"
      ]
    },
    {
      "nr": 941,
      "bereich": "Kinderheim EG - 2. OG",
      "name": "Sockelmontage",
      "start": "2026-05-07",
      "ende": "2026-05-13",
      "dauer_tage": 5.0,
      "ressource": "281.7",
      "outline_level": 3,
      "outline_number": "5.5.30",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5096"
      ]
    },
    {
      "nr": 1042,
      "bereich": "Kinderheim EG - 2. OG",
      "name": "Ausbesserung Türanschlüsse",
      "start": "2026-05-07",
      "ende": "2026-05-13",
      "dauer_tage": 5.0,
      "ressource": "271.0",
      "outline_level": 3,
      "outline_number": "6.6.26",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5185"
      ]
    },
    {
      "nr": 1043,
      "bereich": "Kinderheim EG - 2. OG",
      "name": "Malerarbeiten",
      "start": "2026-05-07",
      "ende": "2026-06-01",
      "dauer_tage": 15.0,
      "ressource": "285.1",
      "outline_level": 3,
      "outline_number": "6.6.27",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5256"
      ]
    },
    {
      "nr": 1044,
      "bereich": "Kinderheim EG - 2. OG",
      "name": "Sockelmontage",
      "start": "2026-05-07",
      "ende": "2026-05-13",
      "dauer_tage": 5.0,
      "ressource": "281.7",
      "outline_level": 3,
      "outline_number": "6.6.28",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5187"
      ]
    },
    {
      "nr": 533,
      "bereich": "Nord",
      "name": "Eternitmontage Laubengänge",
      "start": "2026-05-07",
      "ende": "2026-06-01",
      "dauer_tage": 15.0,
      "ressource": "224.5",
      "outline_level": 3,
      "outline_number": "2.17.6",
      "milestone": false,
      "critical": false,
      "predecessors": [
        "5353",
        "5311"
      ]
    }
  ]
}