  "meta": {
    "projekt": "042 Neubau Pilgerbrunnen",
    "bauherr": "Evangelischer Frauenbund Zürich",
    "architekt": "Müller Sigrist Architekten AG",
    "bm": "Güntensperger Baumanagement AG",
    "quelle": "Terminprogramm_Stand_13-02-2026.pdf",
    "planverfasser": "VATE / MIHA",
    "stand": "2026-02-13"
  },
  "vorgaenge": [
    { "nr": 526, "bereich": "Fassade Gasse", "name": "Eternitmontage Laubengänge", "start": "2026-04-15", "ende": "2026-05-06", "dauer_tage": 15, "ressource": "215.2" },
    { "nr": 532, "bereich": "Fassade Nord", "name": "PU-Abdichtung Nord", "start": "2026-04-15", "ende": "2026-05-06", "dauer_tage": 15, "ressource": "531.525" },
    { "nr": 533, "bereich": "Fassade Nord", "name": "Eternitmontage Laubengänge", "start": "2026-05-07", "ende": "2026-06-01", "dauer_tage": 15, "ressource": "215.2" },
    { "nr": 614, "bereich": "Gärtner Gasse", "name": "Umgebungsarbeiten", "start": "2026-04-21", "ende": "2026-05-12", "dauer_tage": 15, "ressource": "421.0" },
    { "nr": 799, "bereich": "Whg. TH1", "name": "Montage Türblätter Zargentüren", "start": "2026-04-22", "ende": "2026-04-28", "dauer_tage": 5, "ressource": "273.01" },
    { "nr": 801, "bereich": "Whg. TH1", "name": "Malerarbeiten", "start": "2026-04-22", "ende": "2026-05-06", "dauer_tage": 10, "ressource": "285.1" },
    { "nr": 802, "bereich": "Whg. TH1", "name": "Sockelmontage", "start": "2026-05-07", "ende": "2026-05-13", "dauer_tage": 5, "ressource": "281.7" },
    { "nr": 822, "bereich": "KiTa EG", "name": "Montage Garderobe", "start": "2026-04-21", "ende": "2026-04-23", "dauer_tage": 2, "ressource": "273.3" },
    { "nr": 826, "bereich": "KiTa EG", "name": "Malerarbeiten inkl. Zargen", "start": "2026-04-23", "ende": "2026-04-27", "dauer_tage": 2, "ressource": "285.1" },
    { "nr": 827, "bereich": "KiTa EG", "name": "Sockelmontage", "start": "2026-04-27", "ende": "2026-04-29", "dauer_tage": 3, "ressource": "281.7" },
    { "nr": 837, "bereich": "Finish TH1", "name": "Vorabnahme Architekt", "start": "2026-04-29", "ende": "2026-04-29", "dauer_tage": 0, "ressource": "291.0" },
    { "nr": 838, "bereich": "Finish TH1", "name": "Mängelbehebung", "start": "2026-04-29", "ende": "2026-06-01", "dauer_tage": 20, "ressource": "Alle" },
    { "nr": 919, "bereich": "Kinderheim TH2", "name": "Einbau Küche / 4 Stk. + Regenerationsküche", "start": "2026-04-08", "ende": "2026-04-21", "dauer_tage": 10, "ressource": "258.0" },
    { "nr": 921, "bereich": "Kinderheim TH2", "name": "Ausbessern Türanschlüsse", "start": "2026-04-21", "ende": "2026-04-28", "dauer_tage": 5, "ressource": "271.0" },
    { "nr": 922, "bereich": "Kinderheim TH2", "name": "Malerarbeiten", "start": "2026-04-15", "ende": "2026-05-06", "dauer_tage": 15, "ressource": "285.1" },
    { "nr": 931, "bereich": "Kinderheim", "name": "Eingangshalle (Schreinerarbeiten)", "start": "2026-04-17", "ende": "2026-04-30", "dauer_tage": 10, "ressource": "273.3" },
    { "nr": 935, "bereich": "Kinderheim Finish", "name": "Montage Türblätter", "start": "2026-04-21", "ende": "2026-05-06", "dauer_tage": 10, "ressource": "273.3" },
    { "nr": 936, "bereich": "Kinderheim Finish", "name": "Montage Schliessanlage", "start": "2026-04-22", "ende": "2026-04-28", "dauer_tage": 5, "ressource": "275.1" },
    { "nr": 937, "bereich": "Kinderheim Finish", "name": "Signaletik", "start": "2026-04-22", "ende": "2026-04-28", "dauer_tage": 5, "ressource": "278.0" },
    { "nr": 938, "bereich": "Kinderheim Finish", "name": "Kittfugen", "start": "2026-04-22", "ende": "2026-04-28", "dauer_tage": 5, "ressource": "225.1" },
    { "nr": 939, "bereich": "Kinderheim Finish", "name": "Lieferung WM TU", "start": "2026-04-29", "ende": "2026-05-06", "dauer_tage": 5, "ressource": "250.0" },
    { "nr": 989, "bereich": "Kinderheim TH3", "name": "Schleifen Parkett inkl. 1 Behandlung + Abdecken", "start": "2026-04-08", "ende": "2026-04-28", "dauer_tage": 20, "ressource": "281.7" },
    { "nr": 990, "bereich": "Kinderheim TH3", "name": "Montage Küchen", "start": "2026-04-08", "ende": "2026-04-28", "dauer_tage": 15, "ressource": "258.0" },
    { "nr": 991, "bereich": "Kinderheim TH3", "name": "Montage Schreinerarbeiten (Vorhangbretter)", "start": "2026-04-15", "ende": "2026-04-28", "dauer_tage": 10, "ressource": "273.3" },
    { "nr": 992, "bereich": "Kinderheim TH3", "name": "Montage Türblätter Zargentüren", "start": "2026-04-29", "ende": "2026-05-06", "dauer_tage": 5, "ressource": "273.01" },
    { "nr": 993, "bereich": "Kinderheim TH3", "name": "Malerarbeiten", "start": "2026-04-29", "ende": "2026-05-13", "dauer_tage": 10, "ressource": "285.1" },
    { "nr": 1050, "bereich": "IGT", "name": "Mängelbehebung HLKS-E", "start": "2026-04-13", "ende": "2026-05-04", "dauer_tage": 15, "ressource": "HLKS-E" },
    { "nr": 1051, "bereich": "IGT", "name": "Mängelkontrolle / Abnahme HLKS-E", "start": "2026-05-04", "ende": "2026-05-04", "dauer_tage": 0, "ressource": "HLKS-E" },

    { "nr": 1100, "bereich": "Abnahme ET1 (TH1 + KiTa)", "name": "Abnahme Bauherr ET 1", "start": "2026-06-08", "ende": "2026-06-08", "dauer_tage": 0, "ressource": "100", "etappe": "ET1" },
    { "nr": 1101, "bereich": "Übergabe ET1 (TH1 + KiTa)", "name": "Übergabe Bauherr ET 1", "start": "2026-07-06", "ende": "2026-07-06", "dauer_tage": 0, "ressource": "100", "etappe": "ET1" },

    { "nr": 1200, "bereich": "Finish ET2 (TH2 + Kinderheim)", "name": "Vorabnahme Architekt ET 2", "start": "2026-05-13", "ende": "2026-05-13", "dauer_tage": 0, "ressource": "291.0", "etappe": "ET2" },
    { "nr": 1201, "bereich": "Abnahme ET2 (TH2 + Kinderheim)", "name": "Abnahme Bauherr ET 2", "start": "2026-06-22", "ende": "2026-06-22", "dauer_tage": 0, "ressource": "100", "etappe": "ET2" },
    { "nr": 1202, "bereich": "Übergabe ET2 (TH2 + Kinderheim)", "name": "Übergabe Bauherr ET 2", "start": "2026-07-13", "ende": "2026-07-13", "dauer_tage": 0, "ressource": "100", "etappe": "ET2" },

    { "nr": 1300, "bereich": "Finish ET3 (TH4 + Kinderheim)", "name": "Vorabnahme Architekt ET 3", "start": "2026-06-01", "ende": "2026-06-01", "dauer_tage": 0, "ressource": "291.0", "etappe": "ET3" },
    { "nr": 1301, "bereich": "Abnahme ET3 (TH4 + Kinderheim)", "name": "Abnahme Bauherr ET 3", "start": "2026-07-06", "ende": "2026-07-06", "dauer_tage": 0, "ressource": "100", "etappe": "ET3" },
    { "nr": 1302, "bereich": "Übergabe ET3 (TH4 + Kinderheim)", "name": "Übergabe Bauherr ET 3", "start": "2026-07-20", "ende": "2026-07-20", "dauer_tage": 0, "ressource": "100", "etappe": "ET3" }
  ]
}